So many things to finish.
Final inspection schedule for somewhere between March 3 and 5.
I havent posted much because I have been so busy...
Log books are done. Engine, Prop, Airframe and Journey logs. POH is written. Checklists are written. Maintenance manual is written.
Fuel flow test report is done and written.
TC's application for special cert of airworthiness. Done. All 3 copies.
Header tank has been removed, new bungs added, refinished, and reinstalled.
New level sensors for header tank obtained and installed. New monitor board, indicators, and software complete.
Interior placards done. Exterior placards waiting on polishing to be finished.
Paint touch ups done.
Tanks calibrated.
Fuel system leak found and dealt with.
Park brake valve leak found and dealt with.
Dealing with slightly sticky fuel tank sensors in main and auxes. Checked against SB, does not apply. Removed one sensor and checked.
Complete inspection on all control systems complete.
Deflection of all control surfaces verified.
Electrical system diagrams complete and printed.
All required paperwork done.
Went through checklist multiple times.
All exterior placards installed.