The push to get ready for paint is in full swing.
March 17 - 21 days to go
- Starboard aileron counterweight slot and vent cut
- End of wingtip sanded and made flush with the trailing edge of the aileron.
- Sanded the seam... to get ready for a layer of glass.
- Forced night off. Crazy work day...
Wednesday, March 19 - 19 days to go
- Zip... flying club meeting.
Thursday, March 20 - 18 days to go
- Wingtip / aileron closeout started on both wingtips. Foam cut, fit and bonded in.
- Starboard fuselage to strut fairing roughed in and meeting up.
These suckers are a lot of work. Put in on, mark it, take it off, trim, rinse and repeat.
Friday, March 21 - 17 days to go
- More strut fairing. Bolts are back in, holes cut.
- Had lots of visitors... did not get much done.
Saturday, March 22 - 16 days to go
- Thanks to Jim and Bruce, all the fuselage bolts are in and tight! VERY GRATEFUL FOR THE HELP.
- They also got all the fasteners in the hatch covers, and Jim started the starboard wing tip fasteners.
- Weighed the plane. She has gotten fat. Need to check the numbers.
- One layer of glass on the port wingtip closeout. All temp holes have a fiberglass backing. Added glass inside the port wingtip nose to fix the curvature problem.
Sunday, March 23 - 15 days to go
- Thanks again to Jim for helping!
- All nutplates installed for wingtips
- Next round of filler on wingtips
- Aircraft weighted again, but not in level attitude. Weighed about 40 lbs less.
- Covers for flap track pockets cut, fit and drilled.
- Hatch covers installed. Lower hatch cover holes drilled on port side.
- Finished trimming port side strut fairing around tab for wing fold brace. Reinstalled.